Power is where a small pod most often leaves the exemption

A pod can be well under the size line and still need a permit once a cable comes from the house. 10 of the 15 rules here mention power in the exemption text or right beside it.

PlaceWhat the page says about power
SeattlePage does not list wiring in the exemption test. It notes you may need to apply to Seattle City Light for electrical service changes or new services.
PortlandElectrical, plumbing, or heating and cooling work needs trade permits.
Washington CountyNot covered on this page.
DenverA maximum of two lights and two receptacles are permitted with a valid electrical permit.
AustinNew wiring is not on the exempt list for residential electrical work (the list covers items such as cord-and-plug decorative lighting and like-for-like replacements).
PhoenixCity commentary: “If utilities are provided to a detached accessory structure exempt from permit, a permit is required for the installation of the utilities.”
Los AngelesExemption requires that the structure “does not contain any heating, plumbing or electrical installation”.
San JoseNo permit “unless it includes electricity or plumbing”.
San FranciscoLights or outlets are allowed if an electrical permit is obtained and the work is inspected and approved.
OaklandA permit is needed if mechanical, electrical or plumbing work is involved.
San Mateo (city)Not covered on this page.
San Mateo County (unincorporated)Not covered on this page.
Citrus HeightsExemption requires that “no power will be ran to the building”.
Sacramento County (unincorporated)Electrical or plumbing added to an exempt structure requires a miscellaneous permit.
RaleighNot covered on this page.

What the makers ship


Solar does not remove the question

Autonomous offers solar on the WorkPod (3 x 430 W panels) and StudioPod (4 x 460 W panels), each with a 10.2 kWh battery and a 3,000 W inverter limit. None of the 15 rules here addresses solar on an exempt shed, so the electrical rule for your address still decides it. Ask the building office before you assume an off-grid setup is exempt.